The work is carried out by Skanska Norway (70 percent) in cooperation with Skanska UK (30 percent).

The project includes a new psychiatry building with a gross floor area of ​​about 12,000 square meters and a building for somatic care of 33,000 square meters. The project also includes alignment of the infrastructure, energy facilities and demolition of existing hospital buildings.

The contract is based on the IPD model (Integrated Project Delivery), where the parties will cooperate in the implementation phase with common incentives, also including subcontractors. For the project, Skanska has gathered expertise from Norway, Sweden, UK and USA.

Construction work has begun. The Psychiatry building will be completed in March 2019 and the building for somatic care during the first quarter 2021.