The construction contract for Olskroken is divided into two phases. In the first phase, which began in December 2015, Peab and the Swedish Transport Administration have worked together on planning and producing a target price for the project. Now Peab has been awarded the contract for the second phase which is a turnkey contract that includes detail planning and construction.
The project is expected to run until 2025.
The project will be order registered in the second quarter of 2018.
Peab Signs Construction Deal for EUR 276M
Sweden —
Peab has been commissioned to expand one of the most important junctions in the West Sweden railroad system, Olskroken, with railway track overpasses. The customer is the Swedish Transport Administration and the contract is worth EUR 276M.<br />
2018-05-11
Maria Olsson Äärlaht
[email protected]