The complex with approximately 13,700 square metres of net floor space will be built south of the bus station in Ratina, along excellent transport connections, at Hatanpään valtatie 9.
The plan is to start the construction of the property in early autumn 2018, and the project is estimated to be completed in spring 2020. The project's investment size is approximately EUR 41M, and the pre-let rate of the complex is approximately 61 per cent. The project will be implemented in one phase.
The property to be constructed at the corner of Hatanpään valtatie and Tampereen valtatie will consist of two sections, of which one has four and the other seven storeys above the ground. The lower section will adapt to Ratina's old, renovated functionalist buildings through its architecture, and the higher section will have clearer geometry. The purpose is to make most of the higher section's view over Lake Pyhäjärvi. The building will also be connected to Ratina shopping centre, its services and parking facilities.